Industrial AI CoE
Joint initiativeProgramme partners
Current phase · Pilot mobilisationUpdated 15 September 2026

Industrial AI Centre of Excellence • Public progress update

Industrial AI, built for deployment.

A public progress update on the Industrial AI Centre of Excellence—from partnership announcement to a practical architecture, focused pilot portfolio, and implementation roadmap.

01MoU & public launchCoE partnership formalised and publicly announced.
03Working sessionsPlatforms, architecture, data, and delivery model aligned.
02Priority pilotsRenewable assets and pharma quality control.
90Day pathwayA stage-gated route from data readiness to evidence.

Joint solution frame

From signals to action

The proposed architecture connects industrial data, explainable AI, asset operations, and engineering governance—without removing human control from consequential decisions.

01

Industrial data

Machine and shop-floor signals enter through approved sources, including the i4Gujarat / SIM ecosystem.

02

SAMVIT intelligence

Anomaly detection, rare-event reasoning, knowledge graphs, root-cause analysis, and explainable prediction.

03

IBM operations

Maximo turns insight into asset context, alerts, maintenance planning, and work-order workflows.

04

Governed outcomes

QRadar and IBM ELM strengthen security, requirements, testing, compliance, and lifecycle traceability.

Shared design principle: technology supports operators with timely evidence; accountable people remain in control.

Progress to date

The foundation is in place

The initiative has advanced from a public commitment to a defined technology model, a focused pilot portfolio, and an implementation pathway.

Partnership formalised

IBM, IAIRO, and the Government of Gujarat formalised and publicly outlined plans for an Industrial AI Centre of Excellence.

Read coverage

Working model aligned

Joint sessions mapped the roles of Maximo, SAMVIT, QRadar, and IBM Engineering Lifecycle Management.

Pilots focused

Renewable asset intelligence and pharma quality control emerged as the strongest first-wave opportunities.

Data needs defined

The team documented the time-series signals, operating ranges, anonymisation, and quality inputs required for modelling.

Infrastructure planned

IBM and IAIRO consolidated a joint compute, storage, platform, and model-serving blueprint for consideration.

Roadmap prepared

A stage-gated 90-day pathway now connects data readiness, technical integration, evidence review, and scale decisions.

Priority pilot portfolio

Two practical proving grounds

The first pilots are designed around measurable industrial value, explainable intelligence, and a clear path into operational workflows.

Mobilisation track

Renewable asset intelligence

Connect equipment time-series data to SAMVIT reasoning and Maximo asset workflows to surface failures earlier and support faster maintenance decisions.

Anomaly detectionRoot-cause analysisFailure predictionMaintenance workflow
Next evidence gateApproved dataset, asset context, baseline metrics, and a recorded end-to-end demonstration.
Mobilisation track

Pharma quality intelligence

Use process and quality signals to detect abnormal behaviour, trace contributing conditions, and strengthen evidence for regulated decision-making.

Quality variationProcess anomaliesTraceabilityFailure-mode learning
Next evidence gateRepresentative process data, agreed failure modes, success criteria, and stakeholder validation.

Programme timeline

From intent to pilot readiness

Each milestone below is grounded in documented activity. Future outcomes remain subject to partner, customer, and government approvals.

View the complete dated record16 milestones · June–September 2026
  1. Technology showcase and white-paper exchange

    IAIRO shared its Industrial AI framing with IBM at the India Software Lab in GIFT City.

    Completed
  2. MoU signed and CoE plans announced

    The partnership was formalised during the Vibrant Gujarat Regional Conference in Vadodara and entered the public domain through joint media engagement.

    Completed
  3. DST engagement and infrastructure guidance

    The team met Gujarat DST in person and received preliminary guidance on the infrastructure-support pathway.

    Completed
  4. MSME and industry ecosystem engagement

    The team met the MSME Commissioner and secured a route into the NPC and wider industry ecosystem for use-case and data discussions.

    Completed
  5. Policy chatbot opportunity identified

    A support opportunity was identified for the Gujarat Industrial Policy 2026 chatbot alongside the industrial pilot track.

    Completed
  6. Maximo–SAMVIT architecture defined

    The teams mapped industrial asset data and SAMVIT intelligence into Maximo actions and operational workflows.

    Completed
  7. Infrastructure and platform requirements consolidated

    IAIRO prepared the infrastructure-request inputs while the teams assessed IBM ELM and QRadar capabilities for governance and security.

    Completed
  8. Wind and pharma data requests sent

    IAIRO requested sanitised industrial time-series data and defined the leading failure-mode contexts; production data delivery is not yet evidenced.

    Completed
  9. Joint architecture and pilot workshop

    The teams aligned the platform roles, leading sectors, data options, and three-month proof objective.

    Completed
  10. Director ICT roadmap meeting

    The programme met Director ICT Kavita Shah (IAS) to advance the Industrial AI CoE roadmap.

    Completed
  11. Infrastructure blueprint submitted

    The consolidated compute and storage plan was shared with Gujarat DST for guidance on next steps.

    Completed
  12. IBM software-access review opened

    Brand Legal and ISA Legal discussions began for the required Maximo, QRadar, and ELM access; the supporting document is prepared and under review.

    In review
  13. Training-data specification prepared

    The modelling team defined the minimum IBM package: consistently sampled time-series readings and normal operating ranges for every feature.

    Completed
  14. MSME and NPC data-access session scheduled

    A follow-up at the MSME office was planned to progress industrial data access, an NPC workshop, and use-case access; the outcome is not recorded in the reviewed material.

    Outcome pending
  15. i4Gujarat opportunity set shared

    IAIRO shared the SIM understanding note and industrial challenge-problem set with IBM.

    Completed
  16. Funding position reviewed

    The weekly tracker continued to record the IBM Lab / Industrial AI CoE funding route as under discussion.

    Open

Current position

What remains open

The programme has a defined solution frame and pilot pathway. The next gates depend on partner decisions, governed data, infrastructure guidance, and measured proof.

Decision pending

First customer-backed pilot

Wind assets and pharma quality remain the leading candidates. A final customer, accountable leads, and primary operational outcome are not yet evidenced.

Awaiting input

Governed production data

The request and modelling schema are complete. Dataset delivery, consent, anonymisation, retention, and transfer controls still need confirmation.

Guidance pending

Infrastructure allocation

The consolidated baseline was submitted to Gujarat DST on 2 September. Approval, allocation, and provisioning are not yet evidenced.

Proof pending

Live POC and measured result

No live Maximo–SAMVIT integration, recorded demonstration, measured result, or acceptance decision is yet evidenced.

Under discussion

Funding and commercial route

As of the 14 September tracker review, the funder, amount, commitment, and delivery route remained unconfirmed.

Review in progress

Software access and governance

IBM legal review for Maximo, QRadar, and ELM access has started. Partners must also settle IP, data, security, hosting, support, and commercial responsibilities.

Evidence boundary: completed means the activity or document is recorded in the reviewed material. It does not imply funding, infrastructure, production deployment, or customer acceptance unless explicitly stated.

Next phase

Convert alignment into evidence

The programme now moves from design to a tightly scoped proof: one customer context, one approved dataset, one end-to-end workflow, and measurable results.

Secure the foundation

Confirm the pilot customer, governed dataset, CoE infrastructure, and required IBM software access.

Deliver predictive maintenance

Build the asset knowledge graph, health and risk scores, alerts, root-cause analysis, and Maximo workflow.

Add governance and security

Apply IBM ELM for requirements and traceability, with QRadar for cyber and OT monitoring.

Build reusable accelerators

Turn validated patterns into repeatable industry assets and share progress through MSME/NPC forums and a future Vibrant Gujarat event.